MCE Civils Capability
Our capabilities are extensive and include earthworks, trenching, structural footings and foundations, equipment hire, and freight. MCE has an end-to-end approach, comprehensive HSE systems, and highly experienced resources to ensure that your project is completed on time and within budget.
Here are a few examples of sites completed by MCE with commercial references available on request.
Lancelin CMTS Civils
Surveying of the site to ensure correct location and orientation of the mono pole.
Excavation and form work as per the structural design.
Installation of a 100mm concrete binding layer.
15 tonnes of rebar installed, including the installation of a 13-metre cylindrical rebar infill cage, which had to be guyed off to temporary sure foot foundations (capable of an ultimate pull-out strength of 23KN), then aligned for verticality.
135 cubic metres of concrete was poured in 8 hours with the aid of a concrete pump truck.
Civil construction works conducted in difficult weather conditions. As the site was located within the dunes of Lancelin beach, we had to compete with daily wind and sand erosion issues.
Installation of a Rocla SR6-BM 50 metre monopole foundation. The poles full strength is achieved by casting an infill cage into the footing with concrete also being pumped into the pole during installation.
Full handover pack completed and submitted first time right.
Works all conducted with in time frame, safely, efficiently, injury and incident free.
LeBlanc – Tower Foundation Upgrade
Excavation and benching 3 sides of the existing tower foundation.
Scabble 3 x existing concrete faces to within client specifications.
Drill and anchor over 200 x starter bars into existing foundation.
Set out reinforcement bar and pass pre-pour inspection with no issues. Install form work and take crucial measurements to ensure the client specifics have been met.
Ensure to take photographs during the concrete pour showing vibration of the new foundation and even distribution.
Maintain the highest quality of finishing making sure to add any required fall or expansion as per the site design.
Ensure correct 7-, 14- and 28-day tests on the concrete supply have been organised with the supplier.
Re-instate geotextile fabrics, blue metal and earthing to client specifications.
Herne Hill Central
Full Telstra compound extension/Installation on an existing NBN monopole site.
Hut pillar foundation installation.
Full site earthing installation and connection to existing grid. Installation of man proof 1.8m cyclone chain link fence. Installation of fixed and removable bollards.
Vertical and horizontal cable tray installation.
Full LeBlanc Headframe installation at 15m.
Installation of weed mat and blue metal as per Telstra spec. Installation of carrier compliant earthing, weathering and labelling. RLM and photo pack submitted first time right.
Works all conducted with in time frame, safely, efficiently, injury and incident free.